Current Road Works - October 2007

High Road Leyton
Thames Water – Major mains replacement works

Commencing mid-September, these works are planned to carry on until the end of December 2007. These are major works being carried out under their mains replacement project.

The first phases of these works are detailed below:

From junction Church Road to junction Sedgwick Road

20 September – 16 November 2007
Reduction in carriageway width during works
Temporary traffic lights

Kings Head Hill, E4
Thames Water: Major mains replacement scheme

From junction The Ridgeway to junction Pole Hill Road
Completion due 9 November 2007
Temporary traffic lights

Hawthorne Road, E17
Thames Water: Major mains replacement scheme

From junction Forest Road to Hoe Street
Road closure

Markhouse Road, E17
National Grid – Gas mains replacement

These works form part of their major mains replacement scheme. Works will take place from St James Street to Lea Bridge Road over the period October 2007 to January 2008.

Billet Road/Blackhorse Lane, E17
Thames Water: Victorian mains replacement scheme

Temporary traffic signals
Continuous works

Hoe Street, E17
National Grid - gas pipe replacement

Completion due 18 October 2007

Francis Road, E11
LBWF Structural maintenance programme

Carriageway resurfacing and associated footway and kerb works

Hall Lane, E4
LBWF Structural maintenance programme

Carriageway resurfacing and associated footway and kerb works

Keynsham Avenue, IG8
Thames Water - flood alleviation scheme

Road closure and temporary traffic signal
Completion due 29 October 2007

Richmond Road E11
National Grid - gas mains replacement

13 August - 28 October 2007

Chingford Mount Road, E4
National Grid – Gas mains replacement
At junction Finch Gardens

24 September to mid-October 2007

Silverdale Road, E4
Thames Water: constructing new culvert

Road closed
Completion due end of November 2007

High Road Leytonstone, E11
National Grid – gas pipe replacement

From Church Lane to Gainsborough Road
Completion due 22 October 2007